Embassy of Egypt, Athens
Location: Athens
Owner: Arab Rebublic of Egypt
Budget: 94.261 €
Duration: 2 Months
Assignment: 22/04/2016
The project involves dismantling of existing and construction of new water and air-duct networks of the air-conditioning system of the Embassy building, without interrupting the works of the Embassy. The new water networks were constructed from special for air conditioning polypropylene piping system, with corrosion protection. They include the separation in primary and secondary network, installation of collector and inverter-driven pumps, as well as new diodes and regulatory valves to ensure adequate water supply of all fan-coil units in the building. The new air-duct systems include installation of new plenums and flexible air ducts with large cross sections, suitable for unimpeded operation of the fan-coil units.